FAQ retention sum in construction contracts in malaysia (2024)

1. What is “retention sum” commonly referred to in construction contracts?

Retention sum is a sum retained by an employer against interim sums payable to the contractors for work done and will be released to the contractor at a later stage upon fulfilment of certain conditions (depends on the terms and conditions of the construction contracts).

2. What is the purpose of a retention sum?

Retention sum is a form of security given to the employer for the due performance of the construction contract by the contractor.

3. How is the retention sum calculated?

The construction contract would encapsulate how the retention sum shall be calculated. In Malaysia, it is common for the employer to retain 10% of the certified sum in its interim progress certificate.

4. Is there a limit on the amount of retention sum?

It depends on the terms and conditions of the construction contract. However, it is a common practice for parties to set the limit of retention sum at 5% of the contract sum.

5. When will retention sums be released?

Usually, the 5% retention sums will be released in 2 tranches. The 1st moiety will be released upon the issuance of the Certificate of Practical Completion (“CPC”) whereas the 2nd moiety will be released upon the issuance of the Certificate of Making Good Defects (“CMGD”).

6. What is my legal recourse if the employer or main contractor refuses to release the retention sum?

For contracts that fall within the definition of a “construction contract” under Section 4 of the Construction Industry Payment and Adjudication Act 2012 (“CIPAA”), you may commence an adjudication claim against the employer for the release of the retention sum.

Apart from commencing adjudication proceedings, you may also commence court proceedings or arbitration (depending on the dispute resolution clause in your construction contract) against the employer.

7. Can the contractor commence CIPAA proceedings if the construction contract does not make any reference to CIPAA?

Yes. The right to commence CIPAA proceedings is a statutory right conferred by CIPAA. Unlike arbitration, there is no necessity to have a specific adjudication clause in a construction contract.

8. Can the employer set-off its claim for liquidated ascertained damages (“LAD”) against the retention sum due to the contractor?

Whether the employer may set-off its claim for LAD against the retention sum due to the contractor depends on the terms and conditions of the construction contract. All the conditions precedent must be satisfied before the employer is entitled to exercise its right to set-off any claims for LAD against the release of the retention sum.

9. Can the contractor claim for the release of retention sums in adjudication proceedings if the CPC or CMGD has not been issued?

Under Section 25(n) of CIPAA, the Adjudicator is empowered “to decide or declare on any matter notwithstanding no certificate has been issued in respect of the matter.” Hence, the non-issuance of CPC or CMGD is not a bar to the contractor’s claim for the release of the retention sums.

10. What is the contractors’ legal recourse if the employer has been wound up prior to the release of retention sums?

Unless the retention sums are segregated as trust monies, retention sums owed by the employer to the contractors are debts due and payable to the contractor as an unsecured creditor. Under these circ*mstances, the contractor can only file a Proof of Debt against the employer and the appointed liquidator will make a determination on whether to admit the debt.

However, an admission of debt by the liquidator does not guarantee that payment will be made. Unsecured creditors will be the last in the list to be paid after the debts of preferential and secured creditors have been discharged.

11. What are the contractors’ rights against the retention sums if it was set-aside and categorized as trust monies?

In the event the retention sums are set-aside and categorized as trust monies prior to the insolvency of the employer, the retention sums will not form part of the employer’s assets and it will not be used for debt repayment to its creditors. Instead, the employer will be holding the trust monies in trust for the contractor. Accordingly, the fact that the employer has been wound up does not alter the position of the contractors who are the ultimate beneficiaries of the retention sums.

Under these circ*mstances, the contractor’s claim will take priority and the employer’s liquidator is duty-bound to hand over the trust monies to the contractors.

12. A contractor wants to claim that retention sums are trust monies, despite the employer’s failure to segregate the retention sums. Can that contractor rely on the contractual terms that the retention sum is to be held in trust by the employer for the benefit of the contractor to make the claim?

In order to constitute as trust monies, the retention sums must be segregated into a separate account by the employer and this must be done before the employer’s insolvency (See Federal Court in SK M&E Bersekutu Sdn Bhd v Pembinaan Legenda Unggul Sdn Bhd (in creditors’ voluntary liquidation) and another appeal (2019) 3 MLJ 281)

The mere fact that there is a contractual obligation imposed on the employer to hold the retention sums as trustee for the contractor does not automatically render the retention sums as trust monies.

Hence, the contractor would not be able to rely on the contractual terms that the retention sum is to be held in trust by the employer for the benefit of the contractor to claim for the release of the retention sums if the employer failed to segregate the retention sums.

13. What is the prescribed time for the contractor to bring an action against the employer for the release of retention sums?

The limitation period to bring a claim in civil courts against the employer is 6 years from the date of accrual of the cause of action to file their claims.

Check out our Construction Practice Group

REQUEST A FREE CONSULTATION →

Note: This article does not constitute legal advice to any specific case. The facts and circ*mstances of each and every case will differ and therefore will require specific legal advice. Feel free to contact us for complimentary legal consultation.

FAQ retention sum in construction contracts in malaysia (2024)

FAQs

FAQ retention sum in construction contracts in malaysia? ›

How is the retention sum calculated? The construction contract would encapsulate how the retention sum shall be calculated. In Malaysia, it is common for the employer to retain 10% of the certified sum in its interim progress certificate.

What is the retention sum in construction Malaysia? ›

The Retention Sum is a sum retained by the employer from the contractor's work done amount certified in every claims (usually 10% of total work done certified thus subjected to a limit of 5% of contract sum), the purpose of the Retention Sum is to be substantiated as a security for the performance of the contractor and ...

What is the retention money in a construction contract? ›

Retention money is the amount held back to subcontractors from a payment made to them under a construction contract, as a security for their performance. The retention money regime sets out the requirements for holding retention money from subcontractors under the Construction Contracts Act 2002.

What is the retention clause in construction contracts? ›

A construction retention payment (also called retainage) is the amount of money held back until the project is complete. Retainage is usually a percentage of the total project cost. It typically sits at 5% or 10%.

How do you calculate retention rate in construction? ›

Determine the Retainage Rate: First, identify the retainage rate as specified in the contract. Common rates are usually between 5% and 10%. Apply the Rate to Payments: For Total Contract Value: If the retainage is calculated on the total contract value, multiply the total contract amount by the retainage rate.

What is the maximum amount of money held as retention on a contract? ›

While the amount held back as retainage is negotiable, it's usually 5–10% of the contract price, and may be reduced when half the work is completed. This ensures you and the project owner have funds to cover unforeseen expenses, repairs, or subcontractor failings up until the lien waiver.

How do you calculate retention money in a contract account? ›

To ensure that the work carried out by the contractor is as per the plan and specifications, it is monitored periodically by the contractee. This security money upheld by the contractee is known as retention money. Retention money = Value of work certified- Payment made to contractor.

When to release retention money? ›

Critical Analysis for Early Release of Retention Money

1. upon completion of the Works i.e. issuance of Taking Over Certificate (TOC) by the Engineer; 2. Upon Completion of the remedy defects i.e. after expiry of the Defects Notification Periods (DNP);

How to treat retention money in contract costing? ›

The retention payments should be recognized as a trade receivable, because the supplier has the right to invoice the amount to a customer based on the completion of a certain milestone. Let me give you the illustration: Let's say you agreed to build a house with total contract price of CU 100 000 on 1 August 20X1.

What is an example of retention money in a contract? ›

10% of the total value of the Running Account and Final Xxxx will be deducted and retained by the Owner as retention money on account of any damage/defect liability that may arise for the period covered under the defect liability period clause of the Contract free of interest.

What is the reason for retention in construction contracts? ›

For the owner, retainage provides funds should a contractor or subcontractor default on the job. If a contractor can't complete the work agreed on for any reason (e.g., lawsuit, fraud or frozen assets), the funds held in retainage can be used to pay subcontractors or another contractor to finish the job.

When to release retention in construction? ›

Within 60 days of completion of the work, the public entity in charge of the project must release retention to the general contractor within 60 days. The GC must release the respective share of retainage to each subcontractor within 7 days of receiving all or any portion of retainage.

What is the standard retention clause? ›

Standard JCT Retention Clauses. Standard JCT contracts typically stipulate a default retention of 3% if not otherwise specified. This is deducted during interim valuations except in cases where amounts are stated as retention-free.

What is retention calculation? ›

The basic formula for calculating retention is: # of individual employees who remained employed for entire measurement period / # of employees at start of measurement period) x 100.

What is a retention payment? ›

Retention payments are a percentage of milestone payments owed to a subcontractor or vendor. They are withheld pending full practical completion and resolution of any defects. Many project owners or end clients also hold retention payments from monies due to the head contractor at the agreed project milestones.

What is an example of a retention rate? ›

A call center has 65 employees at the beginning of the calendar year, and 49 of them remain at the end of the calendar year. Calculation: 65 – 49 = 16 people left during the calendar year. The retention rate for the call center is 75.3%.

What is the retention sum in PWD Malaysia? ›

Now, as reiterated above, under the PWD Contract, there is no express provision governing retention monies. There are two provisions to safeguard the completion of works and that is performance bond & performance guarantee sum, i.e Clause 13.1 and 13.2 of PWD Contract respectively.

What is a retention receivable in construction? ›

Retention receivable is recorded by general contractors and subcontractors and is the number of funds due from a contractor's customer for retention. Because these funds aren't due until the project is completed, they are recorded in a separate account on the general ledger.

What is retention in JCT contract? ›

Retention is a sum, generally deducted at each monthly payment notice, to provide the client with some security that the contractor/sub-contractor will return to correct any defects during the defects correction period, or defects liability period.

What is the final account in construction Malaysia? ›

In basic terms, a final account in construction contracts is the agreed statement of the amount of money to be paid at the end of a project contract by the employer to the contractor.

Top Articles
Latest Posts
Article information

Author: Kelle Weber

Last Updated:

Views: 5612

Rating: 4.2 / 5 (53 voted)

Reviews: 84% of readers found this page helpful

Author information

Name: Kelle Weber

Birthday: 2000-08-05

Address: 6796 Juan Square, Markfort, MN 58988

Phone: +8215934114615

Job: Hospitality Director

Hobby: tabletop games, Foreign language learning, Leather crafting, Horseback riding, Swimming, Knapping, Handball

Introduction: My name is Kelle Weber, I am a magnificent, enchanting, fair, joyous, light, determined, joyous person who loves writing and wants to share my knowledge and understanding with you.