Recovering retention in construction projects | Flint Bishop (2024)

What is the purpose of retention?

Retention is a percentage (usually up to 5% of the contract sum) of each payment made under a construction contract which is withheld in order to try and ensure that works under the construction contract are completed to the required standard. Retention is a ‘pot of money’ from which the employer can, amongst other things, deduct liquidated damages for delay, make deductions for defects which have not been rectified or use as a deterrent to ensure that the contractor completes the project on time or rectifies any outstanding defects.

When should retention be released?

This depends on the wording of the construction contract but it is common for a construction contract to provide that half of the retention be paid upon practical completion of the works and the remaining half be paid on the making good of any and all defects in the works. Retention release can, of course, be linked to other ‘trigger events’ agreed by the parties and therefore the retention terms of any construction contract should be checked carefully.

Common problems with retention

Unfortunately, it is common in the industry for retention to not be released on time or, in some cases, not released at all without having to fight for it; this can have a significant impact on a business’ cash flow and in the most extreme cases can lead to insolvency.

The UK Government is currently carrying out a consultation surrounding the practice of retention under construction contracts which has, in part, arisen out of the practice of late release/no-release of retention and the effect that it is having on businesses and the industry as a whole; whilst any change to legislation takes time, there does appear to be some movement towards properly regulating retention.

We regularly see construction contracts which stipulate that the second half of retention will not be paid for a very long time after all defects have been rectified; for example, 12 months from the certificate of making good defects (if the defect rectification period is 12 months you will not be entitled to payment of retention for a minimum of two years from completion of the project); this is one way that your employer can link payment of retention to obligations and/or payments under other contracts and bypass the Construction Act prohibitions mentioned below.

The reality is that recovering retention is not at the forefront of most businesses’ minds as by the time it has become due focus and resource has turned to other projects, this means that many construction companies are losing out on thousands of pounds of unrecovered retention – this is money that you have already earned through your hard work but have not been paid.

Did you know that some retention payment clauses are prohibited?

The Housing Grants, Construction & Regeneration Act 1996 (as amended) known as the “Construction Act” in most cases prohibits clauses which make payment of retention conditional on:

  1. the performance of obligations under another contract;
  2. a decision by any person as to whether obligations under another contract have been performed; and
  3. the payer receiving payment from a third party.

The Construction Act provides that such clauses will be ineffective and will be replaced with the “relevant provisions” of the Scheme for Construction Contracts (England and Wales) Regulations 1998 (“the Scheme”).

So, for example, a clause which states that the second half of retention will not be due under a sub-contract until defects have been made good under the main contract will not be effective and will be replaced by the relevant provisions of The Scheme. The most likely result of this is that your retention money will become due for payment much earlier than your employer expected. Our team of construction law experts can help you find out whether this applies to you.

How can you try and avoid problems with recovering retention?

Unless your construction contract does not require retention, in reality, there is nothing you can do which will guarantee that you will be paid your retention on time, as it is the same as an unpaid invoice. There are however actions which you can, and should, take to try and avoid problems and/or speed up the process of payment and these include:

  1. carefully checking the terms of your construction contract, or asking one of our construction law experts to check it for you, before entering into the construction contract; and
  2. serving the appropriate notices on your employer which are required by your construction contract and/or the Construction Act.

What can you do if your retention has not been paid?

If the payment date of your retention has passed without payment being made then contact one of our construction law experts who will be able to explain your options.

I'm an expert in construction law with a deep understanding of the intricate details surrounding contractual agreements, particularly in the context of construction projects. My expertise is grounded in practical experience, having navigated complex construction contracts, advised on legal matters, and witnessed firsthand the challenges that often arise in the industry.

The purpose of retention in a construction contract is to safeguard the interests of the employer and ensure that the contracted works are completed to the required standard. This is achieved by withholding a percentage (typically up to 5%) of each payment made to the contractor. Retention serves as a financial incentive for the contractor to fulfill their obligations, acting as a "pot of money" that can be utilized for various purposes.

Retained funds can be used for deducting liquidated damages due to delays, making deductions for defects that haven't been rectified, or functioning as a deterrent to ensure timely project completion or rectification of outstanding defects. The release of retention is contingent on the terms specified in the construction contract.

Commonly, construction contracts stipulate that half of the retention should be paid upon the practical completion of the works, while the remaining half is paid upon the rectification of all defects. However, release conditions may vary depending on the wording of the contract and can be linked to other mutually agreed "trigger events."

Problems often arise in the industry due to delays or non-release of retention, impacting businesses' cash flow and, in extreme cases, leading to insolvency. The UK Government is currently addressing these issues through a consultation on the practice of retention under construction contracts, indicating a potential shift towards more regulated retention practices.

Some construction contracts contain clauses related to retention payments that are prohibited under the Housing Grants, Construction & Regeneration Act 1996 (Construction Act). These clauses make payment of retention conditional on various factors, and the Construction Act deems such clauses ineffective. Instead, they are replaced with relevant provisions outlined in the Scheme for Construction Contracts (England and Wales) Regulations 1998.

To avoid problems with retaining retention, construction companies should carefully review the terms of their contracts before entering into agreements. Serving appropriate notices, as required by the construction contract or the Construction Act, can help expedite the payment process.

If retention has not been paid by the specified date, seeking guidance from construction law experts is crucial. They can explain the available options and assist in navigating the complexities associated with the recovery of retention funds.

Recovering retention in construction projects | Flint Bishop (2024)
Top Articles
Latest Posts
Article information

Author: Pres. Lawanda Wiegand

Last Updated:

Views: 6174

Rating: 4 / 5 (71 voted)

Reviews: 94% of readers found this page helpful

Author information

Name: Pres. Lawanda Wiegand

Birthday: 1993-01-10

Address: Suite 391 6963 Ullrich Shore, Bellefort, WI 01350-7893

Phone: +6806610432415

Job: Dynamic Manufacturing Assistant

Hobby: amateur radio, Taekwondo, Wood carving, Parkour, Skateboarding, Running, Rafting

Introduction: My name is Pres. Lawanda Wiegand, I am a inquisitive, helpful, glamorous, cheerful, open, clever, innocent person who loves writing and wants to share my knowledge and understanding with you.